    quickstarter pisze:

    http://www.putevi-srbije.rs/index.php/en/
    Ostatni raz jechałem jesienią i uważam że na przejazd całą A1 będziemy musieli jednak poczekać do lata 2020


Prorok uważa pan zielony

A w rzeczywistości:

Section Grdelica - Caričina Dolina, L= 11,8 km
The performance of works is financed by the EIB.
LOT 1 - Roadway and bridges Gornje Polje - Predejane tunnel.
The contractor is JV AZVI SA & TADDEI SpA. The works are in progress.

The anticipated deadline for completion of works is the first quarter of the 2019.



LOT 2 - Roadway and bridges Predejane tunnel - Caričina Dolina.
The contractors are JV Trace group hold plc and Mostovik llc (Bulgaria). The works are in progress.

The anticipated deadline for completion of works is the first quarter of the 2019.



LOT 3 - Predejane tunnel.
The contractor is Consortium Alliance X (Euro Alliance Tunnels JSC and Road & Bridges ltd) - Bulgaria.

The contracted construction works were completed on 26/04/2018.



LOT 3 Е,М, - Electromechanical equipment of Predejane tunnel.
The contract was awarded on 27/9/2018. The Contractor is the Azvirt - Azerbaijan
The anticipated deadline for completion of works is the first quarter of the 2019.



Section Caričina Dolina - Vladičin Han, L= 14,3 km
The performance of works is financed by the EIB.


LOT 4 - Manajle tunnel.
The contractor: Consortium Alliance X (Euro Alliance Tunnels JSC and Road & Bridges ltd) - Bulgaria. The works are in progress.

The anticipated deadline for completion of works is February 28, 2019.

LOT 4 Е,М, – Electromechanical equipment of Manajle tunnel.
The contract was awarded on 27/9/2018 The Contractor is the Azvirt - Azerbaijan

The anticipated deadline for completion of works is the first quarter of the 2019.